Preparations
Procedure
Step 1 Disconnect the terminals between the cable delivered with the alarm beacon and the ECC800
communications cable.
Step 2 Remove the two screws from the alarm beacon and remove the alarm beacon from the door
box.
Figure 6-47 Removing the alarm beacon
Step 3 Route the cable of the new alarm beacon through the cable hole in the right door box and
interconnect the cable with the communications cable on the ECC800-Pro.
Step 4 Secure the new alarm beacon to the right door box using two M3x16 recessed pan head
screws.
Step 5 Simulate a smoky environment under the smoke detector, verify that the alarm beacon works
properly, and then clear the alarm.
----End

6.4.12 Replacing a Rack Environment Unit

Impact on the System
The data of the IT cabinet environment cannot be collected and controlled.
Issue 05 (2020-03-25)
Tools: Phillips screwdriver, step ladder
Material: alarm beacon
Skill requirement: hardware installation engineers