Replacing A Smart Eth Gateway - Huawei V500R003C00 Maintenance Manual

Smart modular data center
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Maintenance Guide
Procedure
Step 1 Remove cables from ports on the iBAT panel. Remove the original iBAT from the battery.
Figure 6-37 Removing an iBAT
Step 2 Secure the new iBAT on the fastener, and connect the iBAT cables.
Step 3 Press the iBOX networking switch for 2 seconds. The RF_Z indicator on the iBOX changes
from blinking green at long intervals to blinking green at super short intervals, which
indicates that the iBOX is being networked.
Step 4 Hold down the iBAT networking switch for 2 seconds. When the RUN/ALM indicator turns
from steady red to blinking green at short intervals, and finally to blinking green at long
intervals, the iBAT connects to the iBOX network. A newly added iBAT will replace the
iBAT that has failed in communication. If multiple iBATs fail in communication, the newly
added iBATs will replace them in ascending order of address.
Step 5 Press the networking switch on the iBOX for 2 seconds. When the RF_Z indicator on the
iBOX and the RUN indicator on the iBAT turn from blinking green at super short intervals to
blinking green at long intervals, the replacement is complete.
Step 6 Log in to the ECC800-Pro WebUI and verify that the iBAT parameters are displayed
normally.
----End

6.4.5 Replacing a Smart ETH Gateway

Impact on the System
The facilities connected to the faulty ETH gateway cannot be monitored on the ECC800.
Preparations
Issue 05 (2020-03-25)
Tools: ESD wrist strap, ESD gloves, Phillips screwdriver, step ladder, labels, marker
Material: ETH gateway