Step 7 Assemble the pad power connector holder.
1.
2.
Figure 6-57 Assembling a pad power connector holder (BOM number: 14190892)
Figure 6-58 Assembling a pad power connector holder (BOM number: 14190242)
Step 8 Connect cables from the power connector to the AC actuator, and route the cables.
Issue 05 (2020-03-25)
Clamp the power connector to the guide rail of the holder.
Install the holder cover using three M4x12 screw assemblies.