1
Power on
Fault
Protection
2
Figure 1:
1 Status indication LEDs
2 LCD display
3 Selection keys for selecting, changing and storing parameters
4 Navigation keys for navigating in the menus
* Arrows shown in the display indicate that the value/menu is
possible to change or scroll
Figure 2: Standard connection PST
Power on
Fault
Figure 3: Top level
2.2
1SXU 132 021 M0201
Chapter 2
Quickstart
This chapter is a short guide on how to connect, configure and start the softstarter in the quickest
and safest way.
2
!
Mounting and installing the softstarter shall be done in accordance with local laws and
regulations and must be performed by authorized personnel only.
Do not change any parameters in the Service Settings menu.
3
2:1 Connection
1. Mount the softstarter according to Chapter 4 " Mounting" .
2. Be aware of the ambient temperature. Derating is required above 40 °C (104 °F). See Chapter
4
3 for more information.
3. Connect the main circuit: terminals 1L1 - 3L2 - 5L3 to the line side and terminals
2T1 - 4T2 - 6T3 to the motor side.
4. Connect the control voltage: terminals 1 and 2 (100-250V 50/60Hz).
5. Connect the functional ground: terminal 3.
Information!
The wire shall be as short as possible, and be connected to the mounting plate.The
mounting plate should also be grounded.
6. Connect the start/stop circuits: terminal 4, 5, 8, 9 and 10 according to Figure 2. 24 VDC only!
7. Verify that the main and control voltage corresponds to the softstarter ratings.
8. Switch on the control voltage.
9. The green "Power on" LED should be lit and the LCD should appear as shown in Figure 3.