Figure 61 Gmt Fuse Module - GE Infinity M Series Installation Manual

High capacity with horizontal distribution, 13 u system with galaxy pulsar plus controller, 22u system with galaxy millennium ii controller, initial/supplemental frame, 22u system with supplemental frame and galaxy millennium ii controller
Table of Contents

Advertisement

NE-M Installation Guide
GMT Module
in -48V positions
GMT6A Module must be installed before load connection is made.
Install GMT Module into specified bullet positions: -48V (Blue) or +24V (Orange).
1
Secure GMT Module Return bus bar to the distribution panel Return bus bar with provided nuts.
Note: Return bus on GMT Module is adjustable for -48V or for +24V installation – see GMT Module Installation
Guide.
Torque to 65 in-lb - 7/16" socket.
Strip Load and Load Return wires 3/8" and secure in the GMT module terminal block.
2
Torque to 13 in-lb - screw driver.
3
Dress and wire tie with service loop to provide strain relief.
4
Verify voltage and polarity between the Return bus and each distribution input bus using a voltmeter.
5
Verify wiring polarity at the input of the load equipment.
Do not install load fuses until the load equipment is ready to be energized.
850050111
Issue 03 August 2017
GMT6A Style Fuse Module (bullet)

Figure 61 GMT Fuse Module

GMT Module
in +24V positions
Max Fuse
12A
Max Wire
12 AWG
Max Module Current
57.6A