NEC E120e-M User Manual page 98

Table of Contents

Advertisement

Chapter 2 Preparations
(2) Removal
Remove the server from the rack in the following procedure.
1. Make sure that the server is turned off and then disconnect the power cord or all interface cables from
the server.
2. Remove screws from front left and right sides of server, and take out the server from rack gently and
carefully.
3. Hold the server firmly and remove it from the rack.
(3) Removing Rails
Remove rails from the rack in the following procedure.
1. Refer to Chapter 2 (2.1.2 Installing the server to the rack or removing it from the rack – Removal(2)
Removal) to remove the server from the rack.
2. While pressing the lever on rail, push the rail toward inside of the rack, then remove it.
98
Important At least three persons are required to remove the server from rack.
Important Be careful not to get your fingers caught in the rails or lever.
Important •
While more than three persons are supporting the bottom part of the server,
slowly pull out the server.
Do not apply load on the server from top when it is being pulled out. Doing so
cause the server to drop.
Express5800/E120e-M User's Guide
2. Installation and Connection

Advertisement

Table of Contents
loading

This manual is also suitable for:

Express5800 seriesN8100-2103fN8100-2104f

Table of Contents