Commissioning Guide (IT Scenario)
Procedure
Step 1 Set SmartLi monitoring parameters.
1.
2.
3.
4.
5.
----End
4.7.2.8 Process of adding a device
Prerequisites
●
●
Issue 02 (2022-12-15)
On the home screen of the SmartLi, tap System Info.
Choose System Info > Settings, enter the user name admin and password
000001, and tap
Tap Communication to set IP address assign to Automatic(DHCP) on the
displayed communication settings screen and the SmartLi is discovered by
ECC800-Pro automatically and is connected to the ECC800-Pro.
After the ECC800-Pro is directly identified and connected, set the lithium
battery view on the ECC800-Pro WebUI.
Drag Lithium Battery Cabinet1 to the gray area to the right of the UPS.
Figure 4-11 Configuring the lithium battery cabinet
You have logged in to the NetEco client using a web browser.
You have the operation rights for Data Center Planning.
Copyright © Huawei Digital Power Technologies Co., Ltd.
.
4 Commissioning Core Devices
59