FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario)
● Before commissioning the fire extinguishing system, remove the electrical
actuator from the container valve of the fire extinguisher cylinder. This prevents
the extinguishant release due to misoperations, and prevents accidental
damage during the commissioning. After the commissioning of the fire
extinguishing system, reinstall the container valve to the electrical actuator.
● To avoid damage to the heat detector, keep a proper distance between the
heating device and the heat detector during the commissioning.
Preparations
Tools: multimeter, smoke pistol, heat gun, flat-head screwdriver, Phillips
screwdriver, step ladder
Documents: fire extinguishing drawings and parameters
Skill requirement: fire engineer
Procedure
Step 1 Remove the electrical actuator from the fire extinguisher cylinder.
Step 2 Switch on the input circuit breaker of the extinguishant control panel, and connect
the battery cables to the extinguishant control panel.
Step 3 Flip the key leftward to Auto & Manual, and set the extinguishant control panel
to Auto & Manual.
Figure 5-10 Auto & Manual indicator position
Issue 02 (2022-12-15)
D ANGER
NO TE
If the electrical actuator is installed on the fire extinguisher cylinder, remove the electrical
actuator from the container valve of the fire extinguisher cylinder.
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 System Commissioning
73