Huawei FusionDC1000A Commissioning Manual page 83

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario)
3.
4.
5.
Step 10 (Optional) Check whether the fire alarm signals are reported to the management
system.
Step 11 Reinstall the electrical actuator on the container valve.
----End
Issue 02 (2022-12-15)
NO TE
– The extinguishant control panel generates a LOCAL FIRE alarm, and Extinguishant
Release indicator turns on. The warning sign is steady on.
– LOCAL FIRE terminal generates a LOCAL FIRE alarm signal.
Figure 5-16 Extinguishant Released indicator on
Reset the extinguishant control panel.
NO TE
Wait for one minute and turn the Enable Control key rightward. After the LCD
changes from EEE to Ad, press Reset on the extinguishant control panel to reset the
extinguishant control panel.
Figure 5-17 Enable Control position
Reset the ejector of the electrical actuator.
Press Reset again to check whether all fire alarms are cleared. After the
alarms are cleared, turn the Enable Control key leftward.
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 System Commissioning
77

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents