Huawei FusionDC1000A Commissioning Manual page 77

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario)
Step 15 Press Reset to reset the fire alarm control panel.
Step 16 (Optional) Check whether the fire alarm signals are reported to the management
system.
Step 17 Reconnect cables to the electromagnetic valve.
Issue 02 (2022-12-15)
NO TE
– Reinstall the heat fire detector in a similar way as reinstalling the smoke detector, as
shown in
Figure
5-7.
– After the smoke detector or heat detector is reinstalled, the corresponding fault
indicator turns off in about 3s.
Figure 5-6 Reference line for smoke detector installation
Figure 5-7 Reference line for heat detector installation
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 System Commissioning
71