Step 2 Remove the baffle plates for the DC power cables.
Figure 5-14 Removing the baffle plates for the DC power cables
Step 3 Connect the DC power cables.
● The screw assembly whose model is subject to the delivery should be tightened
● Partially tighten the nuts of the DC power cables to a torque of 5 N·m when
● The wiring terminal must be installed with heat-shrink tubing at the crimping
● Lay out the DC power cables according to the design, route the cables to the
Issue 08 (2022-11-15)
NO TICE
according to the corresponding standard torque.
securing the cables.
area of the cable conductor to ensure that the electrical clearance between the
conductors is greater than 20 mm.
wiring positions on the corresponding switches, and label the cables.
NO TE
● Tighten the nuts using the socket wrench with an extension rod. The length of the
extension rod is greater than 30 cm. Secure the screw assembly using an adjustable
wrench.
● After connecting the DC power cables, ensure that the OT terminals are properly
attached to and aligned with the copper bar, and that the DC power cables point
vertically downwards.