5.3 Installing DC Power Cables
Prerequisites
●
●
●
Procedure
Step 1 Remove the protective cover
Figure 5-13 Removing the protective cover
Issue 08 (2022-11-15)
Figure 5-12 Routing the ground cables in from the bottom
The ESS is not powered on.
The DC power cables have been pre-buried according to the specifications.
The OT/DT terminals have been crimped according to the specifications. For
details, see
C Crimping an OT or DT
Copyright © Huawei Technologies Co., Ltd.
Terminal.