4.2.2 Connecting the PE Cable for the RS485 Signal SPD

Prerequisites
The ground cable and OT terminals are available.
Procedure
Step 1 Remove 8 mm of the insulation layer from the ground cable using the wire stripper.
Step 2 Insert the bare cable cores into port 3 of the RS485 signal SPD, as shown by (1) in Figure 4-5.
(2016-06-20)
To enhance the anti-corrosion performance of the ground terminal, apply silica gel or paint on it after
connecting the PE cable.
For details about how to make the OT terminal at the other end of the cable, see
Step
2.
Connect the other end of the PE cable to the ground bar.
Ground cable: outdoor copper-core cables with a cross sectional area of 4 mm
AWG are recommended.
OT terminal: M6
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4 Connecting Cables
Step 1
and
2
or 12
39

Advertisement

Table of Contents
loading

Table of Contents