Step 2 Strip 8 mm of the insulation layer at the other end.
Step 3 Remove the terminal block from the SmartLogger DI port.
Remove the terminal block using a flat-head screwdriver.
Step 4 Insert the bare cable cores into the terminal block, as shown by (1) in Figure 4-32.
Figure 4-32 Cable connection for the terminal block
Step 5 Use a flat-head screwdriver to tighten the screws on the terminal block, as shown by (2) in
Figure 4-32.
Step 6 Insert the terminal block into the SmartLogger DI port, as shown in Figure 4-33.
Figure 4-33 Connecting the terminal block
To enable the power grid scheduling function, you need to set the corresponding parameters
(Active Power Control or Reactive Power Control) on the embedded WebUI after connecting
cables. For details, see Active Power Control or Reactive Power Control.
----End