Tools and Materials
Hacksaw
Rubber mallet
cable tie
ESD gloves
Safety goggles
This table may not list some tools required at specific sites. Onsite installation personnel and
technical support personnel should prepare the tools based on site requirements.
Some dedicated tools and installation materials delivered with equipment may not be listed in this
table.
To prevent electric shock, get tools insulated and wear ESD gloves when connecting cables.
Copyright © Huawei Technologies Co., Ltd.
Step ladder (2 m)
Polyvinyl chloride
(PVC) insulation tape
Protective gloves
ESD wrist strap
5 Installation Guide
Hammer drill bits(Φ16)
Marker
Safety helmet
Insulated gloves
34