21.4 Initial commissioning of additional devices

21.4
Initial commissioning of additional devices
Normally, the device has already been commissioned by the machine manufacturer.
You have the option of commissioning the devices subsequently, for example when retrofitting
additional devices.
The "Start-up" softkey has been declared as Manufacturer data class (M).
Procedure
894
1.
Select the "Parameter" operating area.
2.
Press the menu forward key and then the "Easy Extend" softkey.
3.
Press the "Start-up" softkey.
A new vertical softkey bar appears.
4.
Press the "Comm. start-up" softkey to start the commissioning.
Before starting, a complete data backup is made to which you can resort
in an emergency.
5.
Press the "Cancel" softkey if you want to abort commissioning prema‐
turely.
6.
Press the "Restore" softkey to load the original data.
7.
Press the "Device function test" softkey to test the machine manufactur‐
er's intended function.
Operating Manual, 08/2018, 6FC5398-7CP41-0BA0
Milling

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinumerik 840d slSinumerik 840de slSinumerik 828d

Table of Contents