Huawei UPS5000-H User Manual page 151

100 kva power modules
Hide thumbs Also See for UPS5000-H:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
2.
3.
4.
Knock the expansion bolt into the hole until the expansion sleeve completely fits
into the hole. The expansion sleeve must be completely buried under the ground
to facilitate subsequent installation.
Figure 6-93 Drilling holes and installing expansion sleeves
(1) M12 bolt
(4) Expansion sleeve
Step 3 Move the cabinets to the installation positions.
Step 4 Combine the inductor cabinet with other cabinets.
1.
Issue 05 (2021-10-13)
Partially tighten the expansion bolt and vertically insert it into the hole. Knock
the expansion bolt using a rubber mallet until the expansion sleeve is fully
inserted into the hole.
Partially tighten the expansion bolt.
Remove the bolt, spring washer, and flat washer.
NO TICE
Remove the right panel from the UPS cabinet.
Copyright © Huawei Technologies Co., Ltd.
(2) Spring washer
(5) Expansion nut
6 Installation
(3) Flat washer
(6) Concrete floor
141

Advertisement

Table of Contents
loading

Table of Contents