Installing Copper Bars And Cables - Huawei UPS5000-H User Manual

100 kva power modules
Hide thumbs Also See for UPS5000-H:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
Figure 6-402 Installing rectifiers and baffle plates
----End

6.6.5.3 Installing Copper Bars and Cables

1.
2.
3.
4.
Issue 05 (2021-10-13)
Install copper bars and cables by referring to Single UPS Installation (1600
kVA, Three-Phase Three-Wire) > Installation in Top Cabling Configuration
> Installing Copper Bars and Cables.
Install fan power cables by referring to Single UPS Installation (1600 kVA,
Three-Phase Three-Wire) > Installation in Top Air-Flow Configuration >
Installing Cables.
Install the top frame for the top air-flow cabinet (using one top air-flow
cabinet as an example).
Figure 6-403 Installing the top frame
Install the mounting plates for the top air-flow cabinet (using one top air-
flow cabinet as an example).
Copyright © Huawei Technologies Co., Ltd.