Before Powering On; Check Points; Procedures Before Starting Operation - Panasonic FP7 Series User Manual

Cpu unit
Hide thumbs Also See for FP7 Series:
Table of Contents

Advertisement

5.1 Before Powering On

5.1 Before Powering On

5.1.1 Check Points

Once wiring has been completed, check the following points before powering on.

Check Points

Items
1
Attaching Units
2
Wiring
3
Connecting cables
4
Settings of CPU
5
Others

5.1.2 Procedures before Starting Operation

Procedures following installation and wiring and before starting operation are as follows.
1.
Powering on
1. Before powering on, carry out a check while referring to
2. After powering on, check that the POWER LED (Blue) and PROG. LED (Green) are ON on
the CPU unit. When a power supply unit is to be used, check that the power supply unit's
POWER LED is ON.
2.
Entering a project
1. Create a project using the tool software.
2. Use the tool software's "Totally Check Project" function to check for syntax errors.
3.
Checking the output wiring
Use the forced I/O function to check the output wiring.
5-2
● Does the product name of each unit match the device list from the design
stage?
● Are the unit mounting screws properly tightened? Is there any looseness?
● Has the dust-proof sheet been removed from the unit?
● Are the terminal screws properly tightened? Is there any looseness?
● Does the wiring of terminal match the signal name?
● Is the wiring sufficiently thick for the expected current?
● Is the cable securely connected?
● Is the expansion cable properly connected?
● Is the mode switch set to "PROG."?
● Are settings for the card operation switch correct?
● Check if there is any potential for an accident.
Description
"5.1.1 Check
Points".
WUME-FP7CPUH-09