4.5.4 Fire Extinguishing System (CE)

● Semi-annual maintenance of the fire extinguishing system involves system
commissioning. Before the maintenance, inform the related administrative
departments that the fire extinguishing system will be maintained and stop
working.
● Before maintaining the fire extinguishing system, remove the electrical actuator
from the container valve of the fire extinguisher cylinder. This prevents the
extinguishant release due to misoperations, and prevents accidental damage.
● After the maintenance, reconnect the electrical actuator, and inform the
administrative departments that the fire extinguishing system has become
operational.
Table 4-14 Semi-annual maintenance checklist for the fire extinguishing system
Device
Fire
extinguishi
ng system
commissio
ning
Fire alarm
bell
Issue 03 (2022-12-15)
NO TICE
Operation
Commission the
fire extinguishing
system by
following the
instructions in
the Fire
Extinguishing
System
Commissioning
(CE) section in
the
commissioning
guide for the
solution in use.
Flip the key to
Enable Control
on the
extinguishant
control panel
rightward. Press
Silence/Sound
Alarm to start or
abort the fire
alarm bell. Reset
the key to
Enable Control
by flipping it
leftward.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Check Standard
Devices work
properly, and the
management
system displays
related alarms.
The alarm bell
rings normally. The
alarm bell rings
loud and clear
when it is started.
4 Routine Maintenance
Maintenance Guide
Replace the corresponding
component.
1. Check and reconnect
cables to the fire alarm
bell.
2. If the fault persists,
replace the fire alarm
bell.