This topic describes how to start the SmartLogger and set the initialization parameters.

5.1 Power-on Process

This section describes how to check the SmartLogger before power-on and how to power on
the SmartLogger.
Checking Before Powering On the SmartLogger
Check and ensure the following before powering on the SmartLogger.
Power-on Process
Power on the devices in the following sequence: Inverter > SmartLogger > PC terminal.
Step
1
2
3
Issue 12 (2019-01-15)
All cables are intact and well insulated.
All cables are of proper size.
All cables are correctly connected and secured.
The PC terminal refers to a PC where the NetEco1000 is installed.
Operation
Perform the requirements mentioned in
SmartLogger.
Start the inverter and correctly set the communications parameters
(including Address, and Baud rate).
For details about how to set communications parameters, see the user
manual of the corresponding inverter or SUN2000 APP User Manual.
Connect the output terminal of the power adapter for the SmartLogger to
the power port POWER and the input terminal to the AC socket.
Copyright © Huawei Technologies Co., Ltd.