Huawei iSitePower-M User Manual page 65

Hide thumbs Also See for iSitePower-M:
Table of Contents

Advertisement

iSitePower-M (MAP05A1, MAB05B1)
User Manual
No.
Cable
2
AC input power cable
3
AC output power cable
4
Ground cable
Table 7-5 Definition of the stripping length of cables for a parallel box (parallel system scenario)
No.
Cable
1
AC input power cable
from the mains input to
the parallel box
2
Cable from the parallel
box to the iSitePower-M
AC input port
3
Cable from the
iSitePower-M AC output
port to the parallel box
4
AC output power cable
from the parallel box to
the load
5
Main ground cable of
the parallel box
Preparing a Cord End Terminal
Figure 7-2 Preparing a cord end terminal
(1) Cable
Issue 02 (2021-12-30)
1
100 mm
75 mm
N/A
1
L wire: 120 mm
N wire: 120 mm
PE wire: 140 mm
L wire: 410 mm
N wire: 340 mm
PE wire: 240 mm
L wire: 115 mm
N wire: 220 mm
PE wire: 370 mm
L wire: 300 mm
N wire: 325 mm
PE wire: 580 mm
N/A
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Cord end terminal
7 Electrical Connection
2
PE wire: 7 mm
L/N wire: 17 mm
PE wire: 7 mm
L/N wire: 17 mm
7 mm
2
L wire: 16 mm
N wire: 14 mm
PE wire: 14 mm
L wire: 12 mm
N wire: 7 mm
PE wire: 7 mm
L wire: 12 mm
N wire: 7 mm
PE wire: 7 mm
L wire: 16 mm
N wire: 14 mm
PE wire: 14 mm
14 mm
(3) Crimping tool
60

Advertisement

Table of Contents
loading

This manual is also suitable for:

Map05a1Mab05b1

Table of Contents