8.1 System Power-On

● The product must be powered on within 24 hours after being unpacked. During
● When there is no PV input and batteries are out of power, the product cannot
Procedure
Step 1 Turn on the corresponding switch based on the scenario.
Step 2 Switch on the upstream AC input circuit breaker for the iSitePower-M system.
Step 3 After the initial installation and power-on, observe the LED indicator to check the
running status.
----End

8.2 System Commissioning

When the output voltage system is adjusted, the system is powered off and then
restarted. No manual operation is required.
Issue 02 (2021-12-30)
8
NO TICE
maintenance, the power-off time cannot exceed 24 hours.
be started. You need to manually clear the alarm on the app.
If there is PV input, turn on the DC SWITCH.
If there is no PV input, hold down the manual ON/OFF switch for 5s.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
System Commissioning
8 System Commissioning
81

Advertisement

Table of Contents
loading

This manual is also suitable for:

Map05a1Mab05b1

Table of Contents