10.1 Uneven Ground During the Installation

Use washers in the fitting bag to level the ground.

10.2 Tools for Preparing PV Cables

Use dedicated tools to prepare PV cables. Crimping tool model: PV-CZM-41100;
open-end wrench model: PV-MS-HZ

10.3 Special Cables

The battery power cable, battery power connector, and battery communications
cable are customized to be waterproof and moisture-proof. If they are lost or
damaged, contact your installer for replacement. Do not purchase or replace them
by yourself.

10.4 Removing Power Terminals

There are three methods of using the cable removal tool. Select a proper method
based on the actual situation.
Figure 10-1 Usage of the removal tool
(1) Power parallel port for
battery modules
Issue 02 (2021-12-30)
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Battery cascading port
10

FAQs

(3) PV input port
10 FAQs