Completing The Test; Rate-Of-Change Frequency Protection Sapfrc; Verifying The Settings; Multipurpose Protection - Hitachi RED670 Commissioning Manual

Hide thumbs Also See for RED670:
Table of Contents

Advertisement

Section 11
Testing functionality by secondary injection
11.7.2.2

Completing the test

Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore
connections and settings to the original values, if changed for testing purposes.
11.7.3

Rate-of-change frequency protection SAPFRC

Prepare the IED for verification of settings as outlined in section
section
11.7.3.1

Verifying the settings

Verification of START value and time delay to operate
1.
Check that the settings in the IED are appropriate, especially the START value and the definite
time delay. Set StartFreqGrad, to a rather small negative value.
2.
Supply the IED with three-phase voltages at their rated values.
3.
Slowly decrease the frequency of the applied voltage, with an increasing rate-of-change that
finally exceeds the setting of StartFreqGrad, and check that the START signal appears.
4.
Note the operate value and compare it with the set value.
5.
Increase the frequency to rated operating conditions, and zero rate-of-change.
6.
Check that the START signal resets.
7.
Instantaneously decrease the frequency of the applied voltage to a value about 20% lower than
the nominal value.
8.
Measure the time delay for the TRIP signal, and compare it with the set value.
Extended testing
1.
The test above can be repeated to check a positive setting of StartFreqGrad.
2.
The tests above can be repeated to check the time to reset.
3.
The tests above can be repeated to test the RESTORE signal, when the frequency recovers
from a low value.
11.7.3.2
Completing the test
Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore
connections and settings to the original values, if changed for testing purposes.
11.8

Multipurpose protection

11.8.1

Function revision history

Document
revision
A
B
C
D
E
Table continues on next page
194
"Preparing for test"
in this chapter.
Product
History
revision
2.2.1
-
2.2.1
-
2.2.2
-
2.2.3
-
2.2.3
-
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 505 378-UEN Rev. K
"Requirements"
and
GUID-74F9B9A9-91EB-45BA-A883-6BA325C8B272 v1
Line differential protection RED670
Commissioning manual
M16290-52 v5
M16256-2 v6
M16256-8 v1
M16256-10 v5
M16256-29 v4
M16256-39 v4
SEMOD53552-1 v1

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 series

Table of Contents