Checking Of Unblocking Logic; Completing The Test; Phase Segregated Scheme Communication Logic For Distance Or Overcurrent Protection Zpcpsch - Hitachi RED670 Commissioning Manual

Hide thumbs Also See for RED670:
Table of Contents

Advertisement

1MRK 505 378-UEN Rev. K
1.
Deactivate the receive (CR) signal of the IED.
2.
Apply healthy normal load conditions to the IED for at least two seconds.
3.
Apply a fault condition within the forward directed zone used for scheme communication
tripping.
4.
Check that correct trip outputs and external signals are obtained for the type of fault generated
and that the operate time complies with the tCoord timer (plus relay measuring time).
5.
Check that the other zones operate according to their zone times and that a send (CS) signal is
only obtained for the reverse zone.
6.
Check that for a forward fault, carrier send (CS) signal is first obtained from the delta based
fault inception detection (as it is not directional) , and immediately inhibited by the forward
zone.
7.
Activate the IED receive (CR) signal.
8.
Apply a fault condition in the forward directed zone used for scheme communication tripping.
9.
Check that the no trip from scheme communication occurs.
10.
Check that the trip time from the forward directed zone used for scheme communication
tripping complies with the zone timer and that correct trip outputs, external signals, and
indications are obtained for the actual type of fault generated.
11.11.1.6

Checking of unblocking logic

Check the unblocking function (if the function is required) when checking the communication
scheme.
Command function with continuous unblocking (Unblock = 1)
Procedure
1.
Activate the guard input signal (CRG) of the IED.
2.
Using the scheme selected, check that a signal accelerated trip (TRIP) is obtained when the
guard signal is deactivated.
11.11.1.7

Completing the test

Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore
connections and settings to the original values, if changed for testing purposes.
11.11.2
Phase segregated scheme communication logic for distance or
overcurrent protection ZPCPSCH
Prepare the IED for verification of settings outlined in Section
Check the scheme logic during the secondary injection test of the impedance protection functions.
Activating of the different zones and phases verifies that the CSLx signal are issued from the
intended zones. The CSLx signal from the independent tripping zone must have a tSendMin
minimum time.
Check the tripping function by activating the CRLx inputs with the overreaching zone used to achieve
the CACCLx signals.
It is sufficient to activate the zones with all types of fault with the secondary injection.
Line differential protection RED670
Commissioning manual
© 2017 - 2022 Hitachi Energy. All rights reserved
Testing functionality by secondary injection
GUID-33B76F26-DEEF-46C3-A66F-A8713B50E413 v2
"Preparing the IED to verify
Section 11
M13868-72 v4
M13868-76 v6
M13868-84 v6
settings".
219