3.2.2 Installing Batteries

Context
● Before installing batteries, read through the battery safety precautions, obtain
● Wear insulated gloves and use insulated tools to prevent electric shocks or
● Place the batteries in a correct way to prevent vibrations and shocks.
● Install the batteries from the lower layer to the upper layer to prevent falling
Procedure
Step 1 Install a battery rack and batteries.
For details, see the battery installation guide delivered along with batteries.
----End

3.2.3 Installing Optional Components

3.2.3.1 Installing Antiseismic Kits

Procedure
Step 1 Determine the positions for installing the antiseismic kits.
Issue 17 (2023-07-10)
D ANGER
the delivered battery installation guide, and install batteries as instructed.
short circuits.
over due to imbalance.
(With a marking-off template) Determine the installation positions for the
antiseismic kits based on the delivered marking-off template, and mark
mounting holes.
(Without a marking-off template) Mark mounting holes based on the
following figure.