Installing A Return Air Duct - Huawei FusionCol8000-E140 Quick Manual

Modular indirect evaporative cooling system
Table of Contents

Advertisement

FusionCol8000-E140 Modular Indirect Evaporative
Cooling System
Quick Guide (2021, Ireland)
Figure 1-9 Installing the canvas sheet metal and canvas
(1) Position for securing the canvas at the air
supply vent
Step 2 Secure the canvas to the air duct.
Step 3 Wrap the rubber plastic thermal insulation foam (at least 3 cm thick, covered with
aluminum foil) for the canvas.
Figure 1-10 Thermal insulation foam
----End

1.3.5.2 Installing a Return Air Duct

Context
The return air duct needs to be prepared onsite.
The reserved space on the equipment is 2130 mm x 1310 mm.
You are advised to use foam boards to prepare the air duct. Use six screws to
secure a horizontal board and four screws to secure a vertical board. Drill holes
around the air return vent of the equipment by yourself.
Issue 02 (2023-08-03)
Copyright © Huawei Digital Power Technologies Co., Ltd.
1 System Installation
(2) Canvas sheet metal and canvas
15

Advertisement

Table of Contents
loading

Table of Contents