Communication Board Ethernet Cbe20 - Siemens SINAMICS S120 Commissioning Manual

Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

Diagnosis
3.1 Diagnostics via LEDs
3.1.18

Communication Board Ethernet CBE20

Table 3-20
Communication Board Ethernet CBE20 – description of the LEDs
LED
Color
Link port
-
Green
Activity port
-
Yellow
Fault
Red
Sync
Green
OPT on the
Control Unit
Green
126
State
OFF
Electronics power supply is missing or outside permissible
tolerance range.
Continuous
A different device is connected to port x and a physical
connection exists.
OFF
Electronics power supply is missing or outside permissible
tolerance range.
Continuous
Component active (DC link discharge via braking resistor
in progress).
OFF
If the Link Port LED is green:
The CBE20 is operating normally, data is being
exchanged with the configured IO Controller
The response monitoring interval has elapsed.
Flashing
Communications is interrupted.
The IP address is incorrect.
Incorrect or no configuration.
Incorrect parameter settings.
Incorrect or missing device name.
IO Controller not connected/switched off, although an
Ethernet connection has been established.
Other CBE20 errors
Continuous
CBE20 bus error
No physical connection to a subnet/switch.
Incorrect transmission rate
Full duplex transmission is not activated.
OFF
If the Link Port LED is green:
Control Unit task system is not synchronized with the IRT
clock. An internal substitute clock is generated.
Flashing
The Control Unit task system has synchronized with the
IRT clock cycle and data is being exchanged.
Continuous
Task system and MC-PLL have synchronized with the IRT
clock.
OFF
Electronics power supply is missing or outside permissible
tolerance range.
Communication Board either defective or not inserted.
Continuous
Communication Board is ready and cyclic communication
is taking place.
Flashing
The Communication Board is ready, but cyclic
0.5 Hz
communication is not yet taking place.
Possible causes:
At least one fault is present.
Communication is being established.
Description, cause
Commissioning Manual, (IH1), 07/2007 Edition, 6SL3097-2AF00-0BP7
Remedy
Commissioning