8 Installing the IFS06

Figure 8-15 Install the IFS06.

(1) M12x70 bolt
Step 6 Use a level to check whether the feet of the ICR are on a horizontal plane. If not, add adjusting
pads to ensure that the feet of the ICR are on a horizontal plane.
1.
2.
8-10
(2) Spring washer
Pre-tighten the bolts, as shown in

Figure 8-16 Pre-tightening the bolts

Use a level to check whether the feet and bottom beam of the ICR are on a horizontal plane,
as shown in
Figure
8-17.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
(3) Flat washer
Figure
8-16.
DBS3900(ICR)
Installation Guide
(4) Insulating washer
Issue 01 (2011-03-30)