Figure 8-17 Checking And Adjusting The Level Of The Icr; Figure 8-18 Tightening The Bolts - Huawei DBS3900 Installation Manual

Indoor centralized rack (icr) dual-mode base station
Hide thumbs Also See for DBS3900:
Table of Contents

Advertisement

DBS3900(ICR)
Installation Guide
3.
4.
----End
Issue 01 (2011-03-30)

Figure 8-17 Checking and adjusting the level of the ICR

(1) Level
Add adjusting pads to ensure that the feet and bottom beam of the ICR are on a horizontal
plane, as shown in
Figure
NOTE
The adjusting pads should be added at the expansion bolt assemblies.
Tightening the bolts using a socket wrench, as shown in

Figure 8-18 Tightening the bolts

Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
(2) Adjusting pad
8-17.
8 Installing the IFS06
Figure
8-18.
8-11