Section 4
Analog inputs
13.8
kV
120
V
IEC06000600 V5 EN-US
Figure 19:
A Two phase-to-phase connected VT
56
L1
L2
L3
13.8
kV
120
V
Where:
1)
shows how to connect the secondary side of a phase-to-phase VT to the VT inputs on the
IED
2)
is the TRM where these three voltage inputs are located. It shall be noted that for these
three voltage inputs the following setting values shall be entered:
VTprim =13.8 kV
VTsec =120 V
Please note that inside the IED only ratio of these two parameters is used.
Table continues on next page
IED
2
1
1MRK 511 423-UEN A
3
5
SMAI2
BLOCK
REVROT
^GRP2L1
^GRP2L2
^GRP2L3
#Not Used
^GRP2N
4
IEC06000600-5-en.vsdx
Bay control REC650 2.2 IEC
Application manual
AI3P
AI1
AI2
AI3
AI4
AIN
.

Advertisement

Table of Contents
loading

This manual is also suitable for:

RelionRec650

Table of Contents