60
Fix the lead-through plate to the floor:
1. Make a hole in the floor or cable conduit cover below the lead-through plate. See
drawings.
2. Check that the floor is horizontal with a spirit level.
3. Fasten the lead-through plate with screws or bolts.
Note: The screws/bolts will be removed and refastened when the pedestal is fastened through the
same holes later on. The lead-through plate can be fastened after leading the cables through it if
the cabling procedure is more convenient in that way.
Frame size R7
These brackets can be removed for
the time of the installation
W1
V1
R-
U1
U2
a
Installation
Phone: 800.894.0412 - Fax: 888.723.4773 - Web: www.clrwtr.com - Email: info@clrwtr.com
Busbars connecting the
power cable terminals to
the drive module
R+
UDC+
W2
UDC-
V2
PE
a
a floor fixing points
ProE: 64524739
Frame size R8
V2
V1
U1
U2
UDC-
R-
a
Dimensional
W1
W2
UDC+
R+
PE
a
ProE: 64564439