Replacing A Smart Eth Gateway - Huawei FusionModule2000 V500R002C03 Maintenance Manual

Smart modular data center
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Cente
Maintenance Guide
communication. If multiple BIMs fail in communication, the newly added BIMs will replace
them in ascending order of address.
Step 5 Press the networking switch on the CIM for 2 seconds. When the RF_Z indicator on the CIM
and the RUN indicator on the BIM turn from blinking green at super short intervals to
blinking green at long intervals, the replacement is complete.
Step 6 Log in to the WebUI and verify that the BIM parameters are displayed normally.
----End

6.4.5 Replacing a Smart ETH Gateway

Impact on the System
The facilities connected to the faulty ETH gateway cannot be monitored on the ECC800.
Preparations
Procedure
Step 1 Label each cable based on the corresponding ports on the smart ETH gateway.
Step 2 Disconnect cables from the smart ETH gateway.
Step 3 Remove the failure smart ETH gateway from the guide rails.
Figure 6-38 Removing the smart ETH gateway
Step 4 Install the reserved smart ETH gateway in the original position and connect the cables.
Step 5 On the WebUI of the ECC800, choose Monitoring > System > ECC800 > Controls >
Delete device with communication failure, and click Submit.
Step 6 Log in to the ECC800 WebUI, and edit the plan view by adding new devices.
Step 7 Check the parameters and communication status of the smart ETH gateway to ensure normal
communication.
----End
Issue 03 (2019-12-04)
Tools: ESD wrist strap, ESD gloves, Phillips screwdriver, step ladder, labels, marker
Material: ETH gateway