Step 7 Press the CIM networking switch for 2 seconds. The RF_Z indicator on the CIM changes
from blinking green at long intervals to blinking green at super short intervals, which
indicates that the CIM is being networked. Verify that the CIM network is normal.
Step 8 Confirm that each BIM reports information properly.
----End

6.4.4.2 Replacing a iBAT (BIM)

A BIM needs to be replaced when it is faulty or fails in communication. If multiple BIMs
need to be replaced, replace them in ascending order based on battery numbers in the range of
0–300.
Impact on the System
The operation data of the battery managed by the BIM cannot be monitored.
Preparations
Procedure
Step 1 Remove the original BIM from the battery.
Figure 6-37 Removing a BIM
Step 2 Secure the new BIM on the fastener, and connect the BIM cables.
Step 3 Press the CIM networking switch for 2 seconds. The RF_Z indicator on the CIM changes
from blinking green at long intervals to blinking green at super short intervals, which
indicates that the CIM is being networked.
Step 4 Press the new BIM networking switch for 2 seconds.The RUN indicator changes from steady
green to steady red. After you release the networking switch, the RUN indicator changes to
blinking green intermittently at super short intervals, then to blinking red at super short
intervals, and finally to blinking green at super short intervals. The BIM searches for and
connects to the CIM network. A newly added BIM will replace the BIM that has failed in
Issue 03 (2019-12-04)
Material: BIM
Skill requirement: power distribution engineers
Copyright © Huawei Technologies Co., Ltd.
6 Parts Replacement
69

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusionmodule2000

Table of Contents