Step 4 Clamp the new iBOX to the fastener.
Step 5 Reconnect cables to the iBOX based on the cable labels.
Step 6 Synchronize the parameters of the iBOX on the ECC800-Pro WebUI.
Step 7 On the WebUI of the ECC800-Pro, choose Monitoring > System > ECC800 >
Controls > Delete device with communication failure, and click Submit.
Step 8 Hold down the networking switch on the iBOX for 2s. The RF_Z indicator on the
iBOX changes from steady green to blinking green at super short intervals (on for
0.05s and then off for 0.05s), which indicates that the iBOX is being networked.
Step 9 Hold down the iBAT networking switch for 2s. When the RUN/ALM indicator
changes from steady red to blinking green at short intervals, and finally to
blinking green at long intervals, the iBAT connects to the iBOX network.
● It is recommended that iBATs be networked from the positive battery string terminal
● The sequence of connecting the iBAT to the iBOX determines the battery number.
Step 10 Hold down the networking switch on the iBOX for 2s. When the RF_Z indicator on
the iBOX changes from blinking green at super short intervals to blinking green at
long intervals, the networking is complete.
Step 11 Confirm that each iBAT reports information properly.
----End

5.4.4.2 Replacing an iBAT

An iBAT needs to be replaced when it is faulty or fails in communication. If
multiple iBATs need to be replaced, replace them in ascending order based on
battery numbers in the range of 0–300.
Impact on the System
The operation data of the battery managed by the iBAT cannot be monitored.
Preparations
Procedure
Step 1 Remove cables from ports on the iBAT panel. Remove the original iBAT from the
battery.
Issue 01 (2020-12-25)
NO TE
according to the battery cable connection sequence.
Material: iBAT
Skill requirement: power distribution engineers
Copyright © Huawei Technologies Co., Ltd.