FusionModule2000 Smart Modular Data Center
Maintenance Guide (Fusion Module Actuator)
Prerequisites
Procedure
Step 1 Record the position of the signal cable connected to the ECC800-Pro main control
module panel, and then disconnect the signal cable.
Step 2 Loosen the screws on both sides of the ECC800-Pro main control module.
Step 3 Pull the handles on both sides of the ECC800-Pro main control module, and to
remove the main control module.
Figure 5-8 Removing the ECC800-Pro main control module
Step 4 Remove the SIM card and micro SD card from the card slot.
Figure 5-9 Removing a SIM card and a micro SD card
Step 5 Install the spare SIM card and micro SD card into the card slot.
Issue 01 (2020-12-25)
Tools: ESD wrist strap, ESD gloves
Materials: A spare SIM card and a micro SD card of the same model are
available and functional.