Huawei FusionModule2000 Maintenance Manual page 139

Smart modular data center
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Maintenance Guide (Fusion Module Actuator)
Figure 5-87 Installing a smart U space manager (main control box attached to the
top of the cabinet exterior)
(1) Fastener
(4) Asset detection strip (42 U
detection point)
Procedure
Step 1 (Optional) If U Asset Label are faulty, perform the following steps to replace them.
1.
2.
Step 2 (Optional) If the asset detection strip is faulty, perform the following steps to
replace it.
1.
2.
3.
4.
5.
Step 3 (Optional) If the main control box is faulty, perform the following steps to replace
it.
1.
2.
3.
4.
----End
Issue 01 (2020-12-25)
Remove faulty U Asset Label from the customer equipment and the asset
detection strip.
Record the asset according to the commissioning guide.
Label the position of each U Asset Label on the asset detection strip.
Remove all U Asset Label from the asset detection strip.
Remove the faulty asset detection strip.
Install a new asset detection strip in the original position.
Install the U Asset Label in the original positions based on the position labels.
Label each cable based on the corresponding ports on the main control box.
Remove the faulty main control box.
Install a new main control box in the original position.
Connect the cables to the new main control box based on the cable labels.
Copyright © Huawei Technologies Co., Ltd.
(2) UIM20A Expansion Module (3) Main control box
5 Parts Replacement
132