Insert the SATA and power cables into the corresponding ports on the hard
disk. During cable connection, ensure that the metallic plate of the SATA
cable faces upward.
Figure 5-16 Installing SATA and power cables
(1) SATA cable
NO TE
When the VCN510 is delivered, the SATA cable connecting to the hard disk is fixed using
blue tapes. Before installing the hard disk, remove the tapes.
Install a disk in No. 1 position. Place the disk above the No. 1 disk installation
position. Align the preinstalled screws with the cucurbit holes on the bottom
cover of the chassis. Then, horizontally place the disk. Ensure that the screws
are in the holes.
Figure 5-17 Hard disk installation positions
Copyright © Huawei Technologies Co., Ltd.
5 Parts Replacement
(2) Power cable