Maintenance Guide (Fusion Module Actuator)
Procedure
Step 1 Disconnect the upstream fuse for the eLight power supply.
Step 2 Label each cable based on the corresponding ports on the eLight power supply.
Step 3 Remove the cables from the eLight power supply.
Step 4 Remove the old eLight power supply from guide rails.
Step 5 Install the new eLight power supply in the original position and connect the
cables.
Step 6 Connect the upstream fuse for the eLight power supply.
----End
5.4.26 Replacing a Smart U Space Manager (Connected to a
UIM20A Expansion Module)
Impact on the System
The U space status of the equipment cannot be displayed during replacement.
Issue 01 (2020-12-25)
Figure 5-85 Positions of the eLight actuator and power supply (inside the
aisle)
(1) eLight actuator
(3) Upstream fuse
Copyright © Huawei Technologies Co., Ltd.
5 Parts Replacement
(2) eLight power supply
130