Parts Replacement For The Intelligent Battery Monitoring System; Replacing A Ibox (Cim) - Huawei FusionModule2000 V500R002C03 Maintenance Manual

Smart modular data center
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Cente
Maintenance Guide
Figure 6-33 Removing the electronic lock
Step 3 Install the new electronic lock and connect the monitoring cable to the new lock.
Step 4 Log in to the ECC800 WebUI and choose System Settings > Access Right Management.
Set the access permission for the new electronic lock according to the access permission
setting for the faulty electronic lock. Then perform the Synchronize Permission operation.
Step 5 On the ECC800 WebUI, choose Monitoring > System > ECC800 > Controls > Delete
device with communication failure, and click Submit.
Step 6 Verify that the electronic lock is normal.
----End
6.4.4 Parts Replacement for the Intelligent Battery Monitoring
System

6.4.4.1 Replacing a iBOX (CIM)

Impact on the System
The battery data cannot be monitored.
Preparations
Procedure
Step 1 Disconnect cables from the CIM and label the cables.
1.
2.
3.
4.
Issue 03 (2019-12-04)
Material: CIM
Skill requirement: hardware installation engineers
Disconnect the cable from the PoE port.
Disconnect the cable (if there is any) from the COM port.
Disconnect the cable (if there is any) from the BCB port.
Disconnect the cable from the HALL current monitoring port.
Copyright © Huawei Technologies Co., Ltd.
6 Parts Replacement
67