FusionModule2000 Smart Modular Data Center
Product Description (380 V)
Default Button
Table 3-28 Default button description
Name
Default button

3.2.8.2 BIM

The BIM (BIM01C3) is a battery monitoring module that supports 12 V power input and
monitors the voltages, internal resistances, and pole temperatures of batteries.
Features
Appearance
Figure 3-45 shows the appearance of a BIM.
Figure 3-45 BIM appearance
(1) RUN/ALM indicator
Issue 04 (2017-06-30)
Definition
Press and hold the
button for more than
10s but less than 20s.
Monitors the voltages, internal resistances, and pole temperatures of batteries.
Uploads battery data to CIM through wireless communication.
Has the hibernation function:
When the battery supply voltage is lower than 9.6 V for more than 30 minutes, the
BIM automatically powers off.
When the BIM communication has failed for more than 30 minutes and the battery
voltage is lower than 12.6 V, the BIM automatically powers off.
When the BIM has not been networked successfully in more than two days after
power-on and the battery voltage is lower than 12.6 V, the BIM automatically
powers off.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Function
Reset to the default IP address
(192.168.0.10)
(2) Networking switch
3 System Architecture
(3) Panel port
(4) Fastener
55