Step 2 Switch on the battery circuit breakers.
Step 3 Switch on the AC input circuit breaker.
Step 4 Set all the circuit breakers based on site requirements.
Step 5 Observe the power system for 15 minutes. During this period of time, if no alarm (except for
the door status alarm) is generated on the LCD of the SMU, the voltages and currents for
batteries and loads are normal.
Figure 10-4 Battery switch
(1) Battery switch (behind the cover)
----End

10.9 Follow-up Operations

Procedure
Step 1 Reinstall the removed cover or panel (if there is).
Step 2 Take out fireproof mud from the fitting bag. Seal the cable holes in the power cabinet that are
used by using the fireproof mud, and insert rubber plugs into empty cable holes.
Step 3 Bind package entry modules in the battery cabinet.
Step 4 The paint on the cabinet exterior should be intact. If paint flakes off, repaint the area to avoid
corrosion.
Step 5 Lock the cabinet door and hand over the key to the administrator. Clean the site and leave.
----End
Issue 01 (2014-03-12)
The battery switch is in the AUTO position by default before delivery and the system is
under automatic control.
Open the cover and flip the battery switch to MANUAL only when you need to power on
the battery forcibly. Remember to flip the battery back to AUTO after the commissioning.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
10 Commissioning
81

Advertisement

Table of Contents
loading

This manual is also suitable for:

Tbc300a-tca2

Table of Contents