TP48200A-HX09A2 & TBC300A-TCA2
V300R001C07
Installation Guide
Issue
01
Date
2013-10-25
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei TP48200A-HX09A2

  • Page 1 TP48200A-HX09A2 & TBC300A-TCA2 V300R001C07 Installation Guide Issue Date 2013-10-25 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a potentially hazardous situation which, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. NOTICE is used to address practices not related to personal injury. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 4 Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues. Issue 01 (2013-10-25) This issue is the first official release. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    3.5.1 (Optional) Smoke Sensor ............................30 3.5.2 (Optional) Temperature and Humidity Sensor ......................31 3.5.3 (Optional) Water Sensor ............................32 3.5.4 Battery Temperature Sensor ............................. 32 3.5.5 Lamp ..................................33 Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 6 7.2.2 NetEco Management ............................... 58 7.2.3 Third-Party NMS Management (over SNMP) ......................59 7.2.4 Connecting to Huawei BBU (over Dry Contacts, M2000 Management) ..............60 7.2.5 Installing a Communications Cable Between the Battery Cabinet and the Power Cabinet ........62 7.3 Installing DC Output Power Cables ..........................
  • Page 7 10.8 Connecting the Battery Supply ..........................89 10.9 Subsequent Operations ............................. 90 A Associations between Alarms and Dry Contacts on the UIM ........... 91 B Acronyms and Abbreviations ....................93 Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 8: Safety

    When operating Huawei equipment, in addition to following the general precautions in this document, follow the specific safety instructions given by Huawei.  Only trained and qualified personnel are allowed to install, operate, and maintain Huawei equipment.  This product should be used in the environment that meets design specifications.
  • Page 9 Only qualified professional personnel are allowed to install, configure, operate, and disassemble the device.  Only the personnel authenticated or authorized by Huawei are allowed to replace or change the device of the parts of the device (including the software). Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright ©...
  • Page 10: Electrical Safety

    Only qualified personnel are allowed to perform high voltage and AC operations. Before powering on a device, ground the device. Otherwise, personal injury or device damage may be caused by high leakage current. Tools Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 11: Inflammable Environment

    Electrolyte overflow may damage the device. It will corrode metal parts and circuit boards, and ultimately damage the device and cause short circuit of circuit boards. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 12 Keep away metal objects, which may cause battery short circuit, from batteries. If metal objects must be used, first disconnect the batteries in use before performing any other operations. Hazardous Gas Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 13: Working At Heights

    1.1.5 Working at Heights Avoid object falling when you work at heights. When working at heights, fulfill the following requirements:  Only trained personnel can work at heights. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 14 Issue orders with short and explicit words to avoid misoperations.  Ensure that the angle formed by two cables is not larger than 90 degrees. See Figure 1-1. Figure 1-1 Hoisting heavy objects Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 15: Mechanical Safety

    Ensure that the scraps caused by drilling do not enter the cabinet.  Drilling holes without complying with the requirements affects the electromagnetic shielding performance of the cabinet.  After drilling, clean the metal scraps immediately. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 16: Bundling Signal Cables

    Do not bundle signal cables with high current cables or high voltage cables.  Maintain a minimum space of 150 mm between adjacent ties. 1.2 Equipment Safety 1.2.1 Electricity Safety High Electrical Leakage Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 17: Electrostatic Discharge

    Do not touch the vent or cover the vent with cables or other objects.  To prevent electric shocks, do not put your hands into rectifier slots. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 18: Installation Preparations

    TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 2 Installation Preparations Installation Preparations 2.1 Required Tools Figure 2-1 lists the tools that are required for the installation. Use tools with insulated handles. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 19: Technical Specifications

    100 mm x 650 mm x 650 mm base TBC300A-T Battery 900 mm x 650 mm x 650 mm < 56 kg (without batteries) cabinet (excluding the base and protruding part) Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 20: Installation Dimensions

    88.9 mm x 103 mm x 243 mm ≤ 2.5 kg R4850N1 Rectifier 88.9 mm x 103 mm x 243 mm 2.3 Installation Dimensions Figure 2-2 Figure 2-3 show the installation dimensions. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 21 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 2 Installation Preparations Figure 2-2 Combination dimensions Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 22: Requirements For Cable Routing

    Ground cables must not be bound to or tangled with signal cables. There should be an appropriate distance between them to minimize interruptions.  AC power cables, DC power cables, signal cables, and communications cables must be bound separately. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 23 Installation Guide 2 Installation Preparations  Power cables must be routed straight. No joints or welding should be performed on power cables. Use a longer cable if necessary. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 24: Components

    TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 3 Components Components 3.1 Interior Figure 3-1 shows the interior of the TP48200A-HX09A2. Figure 3-2 shows the interior of the TBC300A-TCA2. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 25 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 3 Components Figure 3-1 Interior of the TP48200A-HX09A2 (1) AC output circuit breaker (2) Maintenance socket (3) Load circuit breaker (4) AC SPD (surge protective device) (5) AC input circuit breaker (6) SMU (7) Battery switch (behind the cover)
  • Page 26: Rectifier

    (2) Space for installing batteries (3) Battery rack (4) Package entry module (5) TEC (6) TCUA control box (7) Ground bar 3.2 Rectifier Appearance Figure 3-3 shows a rectifier. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 27 Table 3-1 Indicator description Indicator Color Status Description Green Steady on The rectifier provides output properly. indicator The rectifier provides no output. Alarm Yellow No alarm is generated. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 28: Smu02B

    Blinking at 4 Hz The rectifier is loading an application program. 3.3 SMU02B Appearance Figure 3-5 shows an SMU02B. Figure 3-5 SMU02B appearance Panel Figure 3-6 shows an SMU02B panel. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 29 Steady on The SMU generates a minor alarm. Major alarm No critical or major alarm is generated. indicator Steady on A critical or major alarm is generated. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 30 NetEco NMS Connects to an port 19200 bit/s protocol, YDN upper-level device protocol such as BBU. NOTE All the ports mentioned are protected by a security mechanism. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 31 Signal Description Sends data over RS485. Receives data over RS485. RX232 Receives data over RS232. TX232 Sends data over RS232. PGND Connects to the ground. None N/A. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 32: Uim02C

    Battery temperature sensor Dry contact input DIN1 NOTE ports For the associations between the dry contact input DIN2 ports and alarms, see the appendix. DIN3 DIN4 DIN5 DIN6 Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 33 19200 bit/s protocol lower-level devices such as the battery voltage detector, DC Conditioner. NOTE The COM port supports the security mechanism. Figure 3-9 Pins in the COM port Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 34 Figure 3-10 UIM02C pin numbers Table 3-10 UIM02C pin definitions Silkscreen Pin Definitions TEM-HUM 12 V ENV_TEMP 12 V ENV_HUM WATER 12 V WATER Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 35: Sensors And Lamp

    TEMP1 TEMP2 TEMP2 GATE GATE+ GATE- SMOKE SMOKE 12 V BTEMP BTEMP 3.5 Sensors and Lamp Figure 3-11 shows the installation positions of the sensors and lamp. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 36 Figure 3-11 Installation positions of the sensors and lamp (1) Temperature sensor (2) Door status (3) Temperature and humidity sensor sensor (4) Battery temperature (5) Smoke sensor (6) Lamp sensor (7) Water sensor Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 37: Optional) Smoke Sensor

    3.5.1 (Optional) Smoke Sensor Figure 3-12 Smoke sensor 1 (1) Wiring port (2) Base (3) Indicator Figure 3-13 Smoke sensor 2 (1) Wiring port (2) Base (3) Indicator Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 38: Optional) Temperature And Humidity Sensor

    TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 3 Components 3.5.2 (Optional) Temperature and Humidity Sensor Figure 3-14 Temperature and humidity sensor 1 Figure 3-15 Temperature and humidity sensor 2 Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 39: Optional) Water Sensor

    Installation Guide 3 Components 3.5.3 (Optional) Water Sensor Figure 3-16 Water sensor 3.5.4 Battery Temperature Sensor Figure 3-17 shows a battery temperature sensor. Figure 3-17 Battery temperature sensor Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 40: Lamp

    TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 3 Components 3.5.5 Lamp Appearance Figure 3-18 Lamp Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 41: Installing Cabinets

    Procedure Step 1 Check whether the packing cases are intact. If a packing case is severely damaged or wet, identify the cause and report the issue to your local Huawei office. Step 2 Unpack the cases. Step 3 Check the quantity of components against the packing lists attached to the packing cases. If the quantity differs from that specified on the packing lists, identify the cause and report the issue to your local Huawei office.
  • Page 42: Marking Hole Positions

    The concrete pad on which the cabinet is to be installed is flat. Procedure Step 1 Remove the cover from the cabinet packaging box and find the hole marking-off template on the cover interior, as shown in Figure 4-2. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 43 Step 3 After marking hole positions for installing the first cabinet, mark hole positions for installing the other cabinet according to the marking-off template, as shown in Figure 4-4. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 44: Drilling Holes And Installing Expansion Sleeves

    Step 3 Partially tighten the expansion bolts. Step 4 Remove the bolts, spring washers, and flat washers. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 45: Securing The Cabinet

    Step 2 Place the flat washers, spring washers, and expansion bolts into the mounting holes of the cabinet. Step 3 Secure the expansion bolts. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 46: Combining Cabinets

    Step 2 Place the, flat washers, spring washers and expansion bolts into the mounting holes of the cabinet. Step 3 Tighten expansion bolts to secure the cabinet. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 47: Stacking Cabinets

    This section describes how to stack a power cabinet and battery cabinet. Procedure Step 1 Remove the fasteners blocked on the mounting holes and cable holes at the top of the battery cabinet, as shown in Figure 4-8. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 48 Step 2 Lay down the power cabinet and pad it with a packing case. Step 3 Remove the base from the power cabinet, as shown in Figure 4-9. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 49 Otherwise, the waterproof ring at the bottom of the power cabinet will be damaged. Step 4 Lift the power cabinet and stack it onto the battery cabinet, as shown in Figure 4-10. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 50 Figure 4-10 Lifting and stacking a power cabinet Step 5 Open the door of the lower cabinet. Step 6 Tighten bolts to secure the stacked cabinets, as shown in Figure 4-11. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 51 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 4 Installing Cabinets Figure 4-11 Securing stacked cabinets ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 52: Installing Ground Cables

    Step 4 Connect one end of the equipotential ground cable to the ground bar in the power cabinet, and the other end to the ground bar in the battery cabinet, as shown in Figure 5-1. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 53 Step 4 Connect one end of the equipotential ground cable to the ground bar in the power cabinet, and the other end to the ground bar in the battery cabinet, as shown in Figure 5-2. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 54 5 Installing Ground Cables Figure 5-2 Installing ground cables for stacked cabinets (1) Ground bar in the power (2) Site ground (3) Ground bar in the battery cabinet cabinet ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 55 5-3. Figure 5-3 Installing an equipotential ground cable for added cabinets (1) Ground bar in battery cabinet 1 (2) Ground bar in the added battery cabinet ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 56: Installing Components

    Step 3 Put rectifiers into their slots and push the rectifiers into the cabinet, ensuring that all rectifiers are in good contact with the backplane. Step 4 Close the handle. Step 5 Reinstall the screws in the handle to secure the handle. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 57: Optional) Installing A Lamp

    Step 3 Connect the negative lamp cable to the load circuit breaker F5 of the PDU. Step 4 Connect the positive lamp cable to the RTN+ busbar. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 58: Optional) Installing A Smoke Sensor

    Ensure that the switch on the smoker sensor base faces the cabinet door. Step 3 Secure the smoke sensor to the base, as shown in Figure 6-3. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 59 Step 4 Connect one end of the signal cable to the smoke sensor and the other end to the SMOKE port on the UIM panel, as shown in Figure 6-4. Figure 6-4 Connecting the signal cable for the smoke sensor ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 60: Optional) Installing A Water Sensor

    6 Installing Components 6.4 (Optional) Installing a Water Sensor Procedure Step 1 Secure a water sensor. Figure 6-5 Installing a water sensor in the battery cabinet (in stacked scenario) Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 61 Step 2 Connect the signal cable for the water sensor to the WATER port on the UIM panel, as shown Figure 6-7. Figure 6-7 Connecting the signal cable for the water sensor ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 62: Optional) Installing An Ambient Temperature And Humidity Sensor

    Step 3 Find the fastener for the temperature and humidity sensor at the left of the cabinet top. Step 4 Install a temperature and humidity sensor onto the fastener, as shown in Figure 6-9. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 63 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 6 Installing Components Figure 6-9 Installing a temperature and humidity sensor Step 5 Close the cover for the temperature and humidity sensor. ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 64: Installing Cables

    Step 3 Put away the flat-head screwdriver and check that the signal cables are securely connected. Figure 7-1 Installing a dry contact signal cable (1) Contact plate (2) Dry contact port ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 65: Installing The Communications Cables

    Figure 7-3 Connecting a communications cable (over the FE port) (1) FE port ----End Networking Mode 2: over RS485 Port Step 1 Connect one end of the network cable to the RS485/RS232 port on the SMU. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 66: Third-Party Nms Management (Over Snmp)

    Step 1 Connect the FE port on the SMU by using a network cable, as shown in Figure 7-5. Figure 7-5 Connecting a communications cable (over SNMP) (1) FE port ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 67: Connecting To Huawei Bbu (Over Dry Contacts, M2000 Management)

    TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 7 Installing Cables 7.2.4 Connecting to Huawei BBU (over Dry Contacts, M2000 Management) Procedure Step 1 Alarm signals are sent over dry contacts. Connect the dry contact signal cable to the EXT-ALM port on the BBU, as shown in Figure 7-6.
  • Page 68 In the non-SRAN site based on the BSC6900, the scope is 0 to 15.  In the non-SRAN site based on the BSC6000, the scope is 1 to 16. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 69: Installing A Communications Cable Between The Battery Cabinet And The Power Cabinet

    Step 3 Connect the other end of the communications cable to the COM port on the UIM02C in the power cabinet, as shown in Figure 7-7. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 70 Step 1 Route a communications cable into the battery cabinet and power cabinet through the package entry modules in the cabinets. Step 2 Connect one end of the communications cable to the COM.OUT port on the TCUA in battery cabinet 1. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 71 Step 5 Connect the other end to the COM port on the UIM02C in the power cabinet, as shown in Figure 7-8. Figure 7-8 Installing communications cables for added battery cabinets (1) TCUA in battery cabinet 1 (2) TCUA in battery cabinet 2 ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 72: Installing Dc Output Power Cables

    Step 2 Secure the negative DC output power cable to the corresponding DC output circuit breaker based on the actual load power. Step 3 Secure the positive DC output power cable to the corresponding screw on the RTN+ busbar. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 73 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 7 Installing Cables Figure 7-9 Installing DC output power cables (1) Loads ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 74: Installing The Tcua Power Cable

    Step 4 Secure the positive power cable on the other end to the appropriate screws on the RTN+ busbar, as shown in Figure 7-10 Figure 7-11. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 75 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 7 Installing Cables Figure 7-10 Installing the TCUA power cable for stacked cabinets Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 76: Installing Ac Output Power Cables

    Step 1 Route AC output power cables into the power cabinet through the package entry modules in the battery cabinet and power cabinet. Step 2 Secure the AC output power cables to corresponding AC output circuit breakers Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 77 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 7 Installing Cables Figure 7-12 Installing the AC output power cable ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 78: Installing 110 V Ac Dual-Live Wire Ac Input Power Cables

    Step 1 Route 110 V AC dual-live wire AC input power cables into the power cabinet through the package entry modules in the battery cabinet and power cabinet. Step 2 Secure AC input power cables to appropriate AC input circuit breakers. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 79 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 7 Installing Cables Figure 7-13 Installing 110 V AC dual-live wire AC input power cables (1) Alternating current distribution box (ACDB) ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 80: Optional) Installing Batteries

    When one battery string connects to the system, connect the battery string to battery string position 1. Otherwise, battery currents may not be detected. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 81: Installing Battery Strings

    Ensure that batteries are from the same manufacturer and of the same model and have a close voltage. New and old batteries cannot be used together. Procedure Step 1 Install batteries into the battery compartment in the sequence shown in Figure 8-2. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 82: Installing Copper Bars Between Batteries

    Step 1 Remove the insulation cover from the batteries. Step 2 Install copper bars between batteries. Step 3 Reinstall the insulation covers onto the two batteries in the middle. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 83: Installing Battery Cables

    Step 3 Secure one end of the positive battery cable to the RTN+ busbar in the power cabinet, and the other end to the positive battery terminal in the battery cabinet. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 84 TP48200A-HX09A2 & TBC300A-TCA2 Installation Guide 8 (Optional) Installing Batteries Figure 8-4 Installing battery cables for stacked cabinets Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 85: Installing Antitheft Baffle Plates

    Step 1 Remove heat shrink tubings from the screws on the antitheft baffle plate base in the battery cabinet. Step 2 Install antitheft baffle plate bases using an antitheft wrench. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 86 8 (Optional) Installing Batteries Step 3 Install antitheft baffle plates onto the bases using an antitheft wrench, as shown in Figure 8-6. Figure 8-6 Installing an antitheft baffle plate ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 87: Verifying The Installation

    Check that all cables are arranged neatly and bound properly to their nearest cable ties, and are not twisted or overly bent.  Check that cable labels are properly and securely attached in the same direction. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 88: Commissioning

    Step 4 Measure the voltage between the -48 V busbar and the RTN+ busbar. The value should range from -42 V DC to -58 V DC. ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 89: Setting The Display Language

    10.4 Setting Battery Parameters Set Battery1 connected, Battery2 connected, Battery3 connected, Battery4 connected, battery rated capacity, BLVD enable, battery installation time and volt. test mode as required. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 90: Optional) Setting Sensor Parameters

    Set to Yes or Settings System Config. Para None based Smoke None on site sensor requirements Ambient None Temp. Sensor Ambient None Humi. Sensor Batt. Temp. Sensor 1 Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 91: Optional) Setting The Hibernation Parameter

    10.7.2 (Optional) Setting Parameters Before Using the NetEco Management Networking Mode 1: over FE Port Step 1 Apply to the site or equipment room network administrator for a fixed IP address. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 92 Table 10-8 Communications parameters Main Menu Second- Third-Level Fourth- Fifth-Level Default Setting Level Menu Menu Level Menu Menu Value Parameters Comm. Serial Port Northbound Port Mode Manual Manual Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 93: Setting Parameters Before Using The Snmp Management

    Step 1 Apply to the site or equipment room network administrator for a fixed IP address. Step 2 Set the IP address, subnet mask, and gateway on the LCD, as shown in Table 10-10. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 94 If the SNMP version is SNMPv1 or SNMPv2c, set SNMP Version to SNMPv1&SNMPv2c under SNMP, and then set SNMP Port Number, Read Community Name, and Write Community Name, as shown in Figure 10-2. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 95 Step 6 Under Mib files, click Export to export the Mib file and import it to the NMS. If there is only one NMS, perform Step 6 once. ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 96: Connecting The Battery Supply

    Open the cover and flip the battery switch to MANUAL only when you need to power on the battery forcibly. Remember to flip the battery back to AUTO after the commissioning. Figure 10-4 Battery switch (1) Battery switch (behind the cover) Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 97: Subsequent Operations

    Step 3 The paint on the surface of the cabinet should be kept intact. Therefore, any damaged paint must be repaired. Step 4 Lock the cabinet door and hand over the key to the administrator. Clean the site and leave. ----End Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 98: A Associations Between Alarms And Dry Contacts On The Uim

    ALM5 Reports alarms for battery fuse blown, load fuse blown, and loop disconnection. Default mode (Close: alarm; Open: normal) can be modified as required. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 99 Reports power cabinet fan faults or high temperatures detected by the temperature control unit (TCU) in the power cabinet. Default mode (Close: alarm; Open: normal) can be modified as required. Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 100: B Acronyms And Abbreviations

    BLVD battery low voltage disconnection conducted susceptibility direct current electrical fast transient electromagnetic compatibility electrostatic discharge fast ethernet heater assembly unit HTTPS Hypertext Transfer Protocol Secure Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 101 SNMP Simple Network Management Protocol surge protective device Transmission Control Protocol TCUA temperature control unit A total harmonic distortion user interface module Issue 01 (2013-10-25) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.

This manual is also suitable for:

Tbc300a-tca2

Table of Contents