Figure 4-2 Taking the marking-off template
Step 2 Mark the hole positions based on the marking-off template, as shown in
Figure 4-3 Marking hole positions for installing a single cabinet
(1) Marker
(4) Concrete floor
If cabinets are combined, mark hole positions for installing the other cabinet by performing step 3. If
there is only one cabinet, the procedure ends.
Step 3 After marking hole positions for installing the first cabinet, mark hole positions for installing
the other cabinet according to the marking-off template, as shown in