10.9 Subsequent Operations

Procedure
Step 1 Reinstall the removed cover or panel (if there is).
Step 2 Fasten package entry module.
Step 3 The paint on the surface of the cabinet should be kept intact. Therefore, any damaged paint
must be repaired.
Step 4 Lock the cabinet door and hand over the key to the administrator. Clean the site and leave.
----End