PDU8000 Modular Precision Power Distribution Cabinet
User Manual
Step 5 Install a new SPD module.
Step 6 Switch the SPD circuit breaker to ON.
----End
9.5.6 Replacing the Monitoring Module
Procedure
Step 1 Loosen the two bolts on the monitoring module, as shown by (1) in
Step 2 Open the two crowbars on the monitoring module, as shown by (2) in
Step 3 Gently pull out the monitoring module, as shown by (3) in
Figure 9-15 Replacing the monitoring module
Step 4 Install a new monitoring module.
Step 5 Close the two crowbars and tighten the two bolts on the monitoring module in turn.
----End
9.5.7 Replacing Output Modules
Prerequisites
Issue 01 (2016-02-27)
If the SPD cannot be pulled out, use a tool such as a flat-head screwdriver to lever it out.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
9 Operation and Maintenance
Figure
9-15.
Figure
9-15.
Figure
9-15.
91