4.5 Cable Routing Rules

Binding Cables
Table 4-3 Cable binding rules
No.
1
2
3
4
5
Issue 01 (2016-02-27)
Cable Binding Rule
Power cables and signal cables are bound separately with a distance above
150 mm.
Both ends of a cable are labeled. Labels are clean and correct, and provide
concise and understandable description.
Cable ties are neatly cut without sharp burs, evenly distributed, bound to a
proper strength, and fastened towards the same direction if possible, as
shown in
Figure 4-9
and
Each bundle contains no more than 15 cables, and cables are neatly bound.
Extra cables are coiled neatly and easy to find.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
4-10.
4 Installation Guide
29