4. Secure drive and rear end brackets to stator assem-
bly with four (4) socket head screws and lock washers.
Tighten screws in two (2) stages using the sequence
shown in Figure 51. Final torque on screws should be
from 71 to 97 in- -lb (8 to 11 N- -m).
5. Install connection plate assembly (item 12) to stator:
A. Place connection plate assembly onto stator so
that three (3) terminal screws fit through plate.
B. Secure connection plate assembly to stator with
two (2) torx screws. Torque screws from 25 to 33 in- -
lb (2.8 to 3.8 N- -m).
C. Install three (3) lower jam nuts onto stator termi-
nal screws. Torque nuts from 72 to 88 in- -lb (8 to 9
N- -m).
6. Carefully install armature assembly into the stator.
End of stator must extend completely through bearing in
rear end bracket.
7. Install wave washer (item 5) and retaining ring (item
6) to secure the armature assembly in the rear end
bracket bearing (Fig. 48). Make sure that retaining ring
is fully seated into groove in armature shaft.
8. Slide encoder into drive end bracket and secure with
torx head screw. Torque screw from 25 to 33 in- -lb (2.8
to 3.8 N- -m).
Electrical System
Screw
Tightening
Sequence
Torque
Screws
71 to 97 in- -lb
(8 to 11 N- -m)
4
Page 3A - - 44
1
Figure 51
Workman GTX Electric
3
2