5.3.3 Installing the PDC on an ESD Floor

Context
A support is required when the PDC is installed on an ESD floor. The support
height depends on the height between the ground and the ESD floor.
Procedure
Step 1 Lower the leveling feet of the PDC using an adjustable wrench until all castors are
off the ground and the cabinet is level.
Step 2 Lift the PDC onto the support and align the mounting holes in the PDC with those
in the support.
Step 3 Level the PDC by adjusting the leveling feet.
Figure 5-10 Leveling PDC
(1) Leveling foot
Step 4 Insert four M12 bolts into the mounting holes in the PDC and support, and
partially tighten the bolts.
Issue 04 (2021-04-13)
Scenario 1
Figure 5-11 Securing the cabinet
Scenario 2
NO TE
(Optional) When the PDC installation environment is 5# channel steel and that the PDC
cannot be secured using the mounting holes, secure the PDC using the mechanical part
shown in the following figure.